Four new level-crossings for NLMK – from scratch to commissioning

Our specialists have finished the project to fit 4 unguarded railway crossings at the Novolipetsk Steel facility – No. 91, 192, 184, 272. Our company provided turn-key solution for the customer, starting from designing, digging works, laying the foundation and up to installation of railway equipment and commissioning works.

All four level-crossings are fitted with ESSO-M axle counting system, while all level-crossing signaling dependencies are built around DKU wheel sensors.

Our specialists also equipped the level-crossings with CCTV system, which detects crossing of the stop line by vehicles at closed level-crossing.